Holme Gardens: a case study and a warning to would-be developers
Our client owned a piece of waste ground at the rear of a commercial building, which for 30 years plus had served no purpose to anyone, except fly tippers.
Back in 2004, we tried to get planning permission for additional parking, which was refused because of concerns over additional traffic. In 2005, we applied for planning permission for two houses, which were refused because of a shortage of parking. Following several consultations with the planning department, we applied for and received planning permission for four flats in 2017.
The reasons for the earlier refusals were never aesthetic but always traffic generation, lack of parking, or the removal of a tree (the Planning Department had put a preservation order on a silver birch soon after the car park refusal). Funding now was the next issue, and it took three years to get the land ownership legally split and then funding in place. This now took us up to the COVID pandemic, which was helpful in that we could make use of the extended time given beyond the stipulated three years to commence building.
The next aspect was to ask the Planning Department to approve the intended bricks. The planners made full use, and beyond, of the two months to give the approval of the bricks, leaving us three days for the builder to get the foundations in the ground, or we would default on the planning condition and so lose the planning approval that was so hard won.
In the meantime, we dealt with the contaminated soil that had to be removed, the Party Wall Notice, getting electricity and the internet connected, and all items that had to be organised and paid for prior to commencement. We were lucky in that the more recent onerous requirements regarding flooding and net diversity had not yet come into effect.
Our client asked us at this point to get a modified planning approval, separating it from the existing Victorian terrace, to simplify the foundation design – fat chance! The planners refused the modification. Never mind; we found a technical solution to the foundation issue, and work on site commenced.
The project took 18 months to build; quite long for such a project. Apparently, the builder trusted only one bricklayer, and this bricklayer laid every single brick; meticulously, though, I might add. So, it took an inordinate amount of time to get up to plate level. By now, the builder had taken on other jobs to work on in the meantime, so the following activities were pretty slow. On reflection, we should have set a completion date backed up by financial implications for the builder. Still, after waiting so many years to get the project out of the ground, a few extra months to guarantee a good quality build and good client/ builder relations didn’t seem important. Sadly, the workmanship and this relationship weren’t that good either, in the end.
The four flats that make up Holme Gardens were completed in 2023, and if by now you might be thinking, was it worth it? Well, yes, it was.
The project sum was £370k, with extras, demolition (including asbestos removal) and landscaping costs of £25k (amounting to 7%), bringing the total build cost to £395k without professional and statutory fees. Building Tectonics fees are not going to be disclosed here, but when you think of the effort we put in to getting this project built, it was never enough. But that is what we do, and if we were not so diligent, steadfast, and enduring, the development may not have been built. Or it may not have received so many accolades from locals on how the development fits in with the street scene (it fits in so well that many passersby assume they have always been there). We are not the type of practice that wants to set the world on fire with some egotistical design; we are perfectly happy to design four flats that look like two Victorian terrace houses (although it is a bit galling to an architectural practice when many passersby assume that this building has always been there. New flats? What new flats?).
Even with the stonework detailing on the façade, the triple glazing, the passive stack ventilation system, and other energy saving technology, in a building that looks over a century old, the cost works out at just over £2,000 per square metre. For those not in the know, the norm for flats would be at least £2,400 in this location, at this time, and for a small development.
More important perhaps than the monetary numbers to us is the knowledge that we have produced four dwellings for people to come home to. What I did not understand and still do not understand, after half a century of doing this job, is why, oh why, is it so difficult?
This article appeaers in the AT Journal issue AT Journal ISSUE 156 – WINTER 2025 as "Holme Gardens: a case study and a warning to would-be developers" written by Tony Keller FCIAT, Director and Owner, Building Tectonics Ltd.
--CIAT
[edit] Related articles on Designing Buildings
- Avoiding planning permission pitfalls.
- CIOB Planning Protocol 2021.
- Community Infrastructure Levy.
- Consultation process.
- Design and access statements.
- How long does it take to get planning permission.
- How long does planning permission last.
- Outline planning application.
- National Planning Policy Framework.
- Neighbourhood planning.
- Planning appeal.
- Planning fees.
- Planning conditions.
- Planning obligations.
- Planning objection.
- Planning performance agreement.
- Planning permission.
- Pre-application advice.
- Statutory approvals.
- Statutory authorities.
- Town and Country Planning Act.
Featured articles and news
The Home Energy Model and its wrappers
From SAP to HEM, EPC for MEES and FHS assessment wrappers.
Future Homes Standard Essentials launched
Future Homes Hub launches new campaign to help the homebuilding sector prepare for the implementation of new building standards.
Building Safety recap February, 2026
Our regular run-down of key building safety related events of the month.
Planning reform: draft NPPF and industry responses.
Last chance to comment on proposed changes to the NPPF.
A Regency palace of colour and sensation. Book review.
Delayed, derailed and devalued
How the UK’s planning crisis is undermining British manufacturing.
How much does it cost to build a house?
A brief run down of key considerations from a London based practice.
The need for a National construction careers campaign
Highlighted by CIOB to cut unemployment, reduce skills gap and deliver on housing and infrastructure ambitions.
AI-Driven automation; reducing time, enhancing compliance
Sustainability; not just compliance but rethinking design, material selection, and the supply chains to support them.
Climate Resilience and Adaptation In the Built Environment
New CIOB Technical Information Sheet by Colin Booth, Professor of Smart and Sustainable Infrastructure.
Turning Enquiries into Profitable Construction Projects
Founder of Develop Coaching and author of Building Your Future; Greg Wilkes shares his insights.
IHBC Signpost: Poetry from concrete
Scotland’s fascinating historic concrete and brutalist architecture with the Engine Shed.
Demonstrating that apprenticeships work for business, people and Scotland’s economy.
Scottish parents prioritise construction and apprenticeships
CIOB data released for Scottish Apprenticeship Week shows construction as top potential career path.
From a Green to a White Paper and the proposal of a General Safety Requirement for construction products.
Creativity, conservation and craft at Barley Studio. Book review.
The challenge as PFI agreements come to an end
How construction deals with inherited assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.